5 Marla House Construction Cost (2250 Sqft) – Full Budget & Material Guide 2026

Introduction

Building a 5 marla house in Pakistan is one of the most exciting steps in life—but it can also feel overwhelming when you don’t know how much money you’ll actually need. Prices of materials keep changing, labour rates fluctuate, and every contractor quotes differently. So what’s the real cost for a 5 Marla (2250 sqft) house in 2025?

This guide breaks down everything step-by-step, with a complete material list, accurate cost estimates, labour charges, and tables + charts to help you plan the perfect construction budget.

Let’s dive in!


Overview: 5 Marla House (2250 Sqft) Construction

A standard 5 marla plot usually has:

  • Plot size: 25 × 45 ft
  • Covered area: Ground + First Floor = 2250 sqft (approx.)
  • Ideal for: Double story home

Covered Area Breakdown

  • Ground Floor: approx. 1150 sqft
  • First Floor: approx. 1100 sqft
  • Total: 2250 sqft

Type of Structure

We assume:

  • Double-story house
  • Normal quality finishes (not ultra-luxury)
  • Standard layout:
    • 3–4 bedrooms
    • 4 bathrooms
    • 1 kitchen
    • TV lounge
    • Drawing room

Grey Structure Cost Breakdown (2250 Sqft)

The grey structure includes:

✔ Foundation
✔ Bricks
✔ Cement
✔ Crush
✔ Steel
✔ Plumbing rough-in
✔ Electrical rough-in
✔ Plaster
✔ Roof concrete

Below is the detailed breakdown.


Foundation & Excavation

ItemQuantityRateCost
Excavation1 jobRs. 45,00045,000
Backfilling1 jobRs. 30,00030,000
Foundation concrete900 sqftRs. 220/sqft198,000

Subtotal: Rs. 273,000


Bricks / Blocks

Approx bricks needed:

  • 105,000 bricks
ItemQuantityRateCost
A+ Bricks105,000Rs. 22/brick2,310,000

Cement, Sand & Crush

Cement

  • Required bags: 1100 bags
  • Rate: Rs. 1,240 per bag
  • Total: Rs. 1,364,000

Sand

  • Sand (Ravi & Chenab): 2,000 cft
  • Avg rate: Rs. 120/cft
  • Total: Rs. 240,000

Crush

  • Total crush required: 1,600 cft
  • Rate: Rs. 220/cft
  • Total: Rs. 352,000

Steel (Rebar)

  • Total steel: 9 tons
  • Rate: Rs. 270,000 per ton
  • Total: Rs. 2,430,000

Plumbing Rough-In

ItemCost
PPRC pipes110,000
Sewerage pipes95,000
Water tanks & fittings45,000

Subtotal: Rs. 250,000


Electrical Rough-In

ItemCost
Wiring110,000
Conduits75,000
Breakers & DB box55,000

Subtotal: Rs. 240,000


Roofing, Lantern & Concrete Work

ItemCost
Shuttering210,000
Lantern concrete165,000
Roof insulation55,000

Subtotal: Rs. 430,000


Grey Structure Labour Cost

Labour rate: Rs. 550 per sqft

2250 × 550 = Rs. 1,237,500


Total Grey Structure Cost

CategoryCost
Foundation273,000
Bricks Work2,310,000
Cement/Sand/Crush1,956,000
Steel2,430,000
Plumbing250,000
Electrical240,000
Roof Work430,000
Labour1,237,500

Total Grey Structure Cost = Rs. 9,126,500

(9.12 Million)


Finishing Cost Breakdown (2250 Sqft)

Finishing includes:

✔ Tiles & marble
✔ Woodwork
✔ Paint
✔ False ceiling
✔ Electric items
✔ Kitchen & bath fittings
✔ Windows & doors

Let’s break it down.


Flooring – Tiles & Marble

ItemQuantityRateTotal
Floor tiles2000 sqftRs. 320/sqft640,000
Bathroom tiles400 sqftRs. 350/sqft140,000
Marble staircase50 rftRs. 950/rft47,500

Subtotal: Rs. 827,500


Woodwork (Doors, Wardrobes, Kitchen)

ItemCost
Wooden doors7 doors
Wardrobes2 rooms
Kitchen cabinets1 kitchen

Subtotal: Rs. 555,000


Paint & False Ceiling

ItemCost
Interior paint210,000
Exterior paint85,000
False ceiling160,000

Subtotal: Rs. 455,000


Windows & Glass Work

ItemCost
Aluminium windows210,000
Glass railing55,000

Subtotal: Rs. 265,000


Sanitary Fittings

ItemCost
WC, basins135,000
Bath sets75,000
Accessories45,000

Subtotal: Rs. 255,000


Electric Fittings

ItemCost
Lights85,000
Switches & sockets55,000
Fans60,000

Subtotal: Rs. 200,000


Kitchen & Bath Accessories

ItemCost
Hood & Hob75,000
Kitchen sink12,000
Shower cabins40,000

Subtotal: Rs. 127,000


Finishing Labour Cost

  • Rs. 400 per sqft
  • 2250 × 400 = 900,000

Total Finishing Cost

CategoryCost
Flooring827,500
Woodwork555,000
Paint & Ceiling455,000
Windows265,000
Sanitary255,000
Electrical fittings200,000
Kitchen/Bath127,000
Labour900,000

Total Finishing Cost = Rs. 3,584,500

(3.58 Million)


🎉 Total Construction Cost Chart (Grey + Finishing)

Bullet Chart

  • Grey Structure: Rs. 9.12 Million
  • Finishing: Rs. 3.58 Million
  • Misc Costs (gate, grills, UPS wiring, extra woodwork): Rs. 500,000

🟩 Grand Total House Construction Cost (2250 sqft)

Rs. 13,200,000 (13.2 Million PKR)

This is the realistic 2025 cost including all materials and finishing.


Complete Material List for 2250 Sqft

MaterialQuantity
Bricks105,000
Cement1100 bags
Crush1600 cft
Sand2000 cft
Steel9 tons
Plumbing pipesComplete set
Electric wiringComplete set
Tiles2000 sqft
Paint20+ drums
Wood doors7
WindowsFull house

Construction Timeline

StageDuration
Grey structure3–3.5 months
Finishing2–2.5 months
Total Time5–6 months

Office 2, 3rd Floor, Big City Plaza, Gulberg-III, Lahore

Email: info@alhassanbuilders.com

Phone: +92 (300) 0045 681